You know you’re good when your competitor hires you to do work they’re scared of – as in the case of the Mohawk Building. The Mohawk Building was scheduled for demolition as part of the Rookery Block demolition project undertaken in downtown Spokane in the spring of 2007.
Talisman was hired to carefully and safely disconnect the Mohawk building from the adjacent historic structure and demolish the eight story building. Talisman was asked to complete work that was contracted to a “competitor” utilizing our Brokk Demolition Robots.
All work was completed without damage to the adjacent historic unreinforced masonry structure. The pictures tell the story.